outp

My Cart

State whether the following statements are True or False. Give reason

Question


State whether the following statements are True or False. Give reason in support of your answer. 
a) If the average number of defects in an item is 4, the upper control limit of the c-chart will be 12.
b) The specification limits and natural tolerance limits are same in statistical quality control.
c) If the probability of making a decision about acceptance or rejection of a lot on the first sample is 0.80 and the sizes of the first and second samples are 10 and 15, respectively, then
the average sample number for the double sampling plan will be 25.
d) Two independent components of a system are connected in series configuration. If the reliabilities of these components are 0.1 and 0.30, respectively then the reliability of the system will be 0.65.
e) A point in the pictorial representation of a decision tree having states of nature as immediate sub-branches is known as decision point. 

 


Posted on : 2023-02-14 12:47:40 | Author : IGNOU Academy | View : 30

Click Here to Order on WhatsApp

Login or SignUp to View Answer / Comment or Ask Question.. Its Free

Word Count : 364

a) False. The upper control limit (UCL) of a c-chart is not fixed and is calculated using a formula based on the average number of defects. The formula for the UCL is usually UCL = avg + 3 * sqrt(avg), where avg is the average number of defects. So, if the average number of defects is 4, the UCL will not be 12.

b) False. The specification limits and natural tolerance limits __ ___________ ____ _____ ___ ____________ ________ ___________ _____________ _____________ _________ ____________ ____.
______ _____________ ______ ____________ _____________ ____________.
_________ _____________ __________ __________ ____________ __________ ____________ ____ ________ _____.
_______ ___ _________ ___________ ________ __ ________ ________ _________ ___________ _____________ ____________.
__________ _____ __ _____________ _____________ _______ ___________ __________ ____ __________ ___ __________.
__ ______ ____________ ____ __ ______ __________ _______ ____ ____________ ____ ____________ ________ _____.
____________ ___ _________ __________ __________ _________ _____ __ __ _____________ ___________ _____________.
__________ ___ _____ ____________ ______ ___.
_______ ______ _______ ____ __________ ________ _____ __ __________.
___________ ____________ _________ _____________ _________ _____ __________ ______ _____ _____________ ___________ _______ ___________ _____ _______.
__________ ____ ____ ____________ __________ ______ _______ ____ __ __ ___________ _________.
___ ____ ___ _____________ ________ ___ ____ ___________ ____________ ______.
_____________ _____ __ _____________ _____________ ___________ _________ _________ _____ _________ ____________ _____________ ________ _____________ ____.
__________ ____________ _________ ____________ ___________ ____ __________ ___________ _______ ___ _____________ _____ _________ ________.
______ __________ __ ___________ ______ ________ _____________ __________ _____ _______ __ _____.
______ __ __________ ___________ ________ __________ _____________ _____.
_______ ___________ ________ ______ __ ___ ___.
________ _____________ _______ ____ ___________ _____ ______ ____ __ ____ _____ ___ ______ ______ _______.
____ ________ _________ ___ _____ ___________ __ ____ _____________ _____________.
__________ ____________ ____________ _______ __________ ___ __________ __ ________ ___________ ____ _____________.
_____ ___________ _____ ______ __ ________ ____________ _______ ________ ________ ____________.
____ ____ __ _____________ ___ _______ _______ _________ ________ ____________ ___ ___ _____ __________.
__ _____________ ___________ ________ ____________ ______ ___________ __ ____________ ______ __________ ______ _____.
____ _______ ___________ ___________ ____________ ____________ ___________ ___ _____ ___________ ___ _______ ___ ________.
_______ _________ ________ ____ _____________ ____________ __ _____________ _____ __ _______ ____.
_____ ________ ______ ____________.
Click Here to Order Full Assignment on WhatsApp








Degree : PG DIPLOMA PROGRAMMES
Course Name : Post Graduate Diploma in Applied Statistics
Course Code : PGDAST
Subject Name : Industrial Statistics-I
Subject Code : MSTE 1
Year : 2023



IGNOU MSTE 1 Solved Assignment 2023
Click Here to Order on WhatsApp

Related Question


The system shown below is made up of ten components. Components 3, 4 and 5 are not identical and at least one component of this group must be available for system success. Components 8, 9 and 10 are identical and for this particular group it is necessary that two out of the three components functions

What is the system reliability if R1 = R 3 = R 5 = R 7 = R 9 = 0.85 and
R 2 = R 4 = R 6 = R 8 = R10 = 0.95

A small electronic device is designed to emit a timing signal of 200 milliseconds (ms) duration. In the production of this device, 10 subgroups of four units are taken at periodic intervals and tested. The results are shown in the following table: 

Subgroup Number Duration of Automatic Signal (in ms)
a b c d
1 195 201 194 201
2 204 190 199 195
3 195 197 205 201
4 211 198 193 180
5 204 193 197 200
6 200 202 195 200
7 196 198 197 196
8 201 197 206 207
9 200 202 204 192
10 203 201 209 192

 i) Estimate the process mean and standard deviation. 
ii) Determine the centre line and control limits for the process mean and process variability.
iii) By plotting the charts on graph paper, determine that the process is stable or not with respect to the process mean and process variability. If necessary, compute revised control limits


State whether the following statements are True or False. Give reason in support of your answer. 
a) If the average number of defects in an item is 4, the upper control limit of the c-chart will be 12.
b) The specification limits and natural tolerance limits are same in statistical quality control.
c) If the probability of making a decision about acceptance or rejection of a lot on the first sample is 0.80 and the sizes of the first and second samples are 10 and 15, respectively, then
the average sample number for the double sampling plan will be 25.
d) Two independent components of a system are connected in series configuration. If the reliabilities of these components are 0.1 and 0.30, respectively then the reliability of the system will be 0.65.
e) A point in the pictorial representation of a decision tree having states of nature as immediate sub-branches is known as decision point. 

 


To monitor the manufacturing process of mobile phones, a quality controller randomly selected 100 mobile phones from the production line, each day over 15 days. The mobile phones were inspected for defectives and the number of defective mobile phones found each day was recorded. The data are given below:

Subgroup Number Number of Mobile Phones Inspected Number of Defective Mobile Phones
1 100 3
2 100 6
3 100 4
4 100 6
5 100 20
6 100 2
7 100 6
8 100 7
9 100 3
10 100 0
11 100 6
12 100 15
13 100 5
14 100 7
15 100 6

 i) Determine the trial centre line and control limits for the fraction defective using the above data. 

ii) Contract the control chart on graph paper and determine that the process is stable or not. If there is any out-of-control point, determine the revised centre line and control limits.


Solve the two-person zero-sum game having the following payoff matrix for player A

  Player B
B1 B2 B3 B4 B5
Player A A1 3 4 5 –2 3
A2 1 6 –3 3 7

A shirt manufacturing company supplies shirts in lots of size 250 to the buyer. A single sampling plan with n = 20 and c = 1 is being used for the lot inspection. The company and the buyer decide that AQL = 0.04 and LTPD = 0.10. If there are 15  defective in each lot, compute the
i) probability of accepting the lot. 
ii) producer’s risk and consumer’s risk. 
iii) average outgoing quality (AOQ), if the rejected lots are screened and all defective shirts
are replaced by non-defectives. 
iv) average total inspection (ATI). 


The failure data of 10 electronic components are shown in the table given below:

Failure Number 1 2 3 4 5 6 7 8 9 10
Operating Time (in hours) 3 5 31 51 76 116 140 182 250 302

Estimate, the
i) reliability. 
ii) cumulative failure distribution.
iii) failure density. 
iv) failure rate functions.

Call Now
Contact Us
Welcome to IGNOU Academy

Click to Contact Us

Call - 9199852182 Call - 9852900088 myabhasolutions@gmail.com WhatsApp - 9852900088
New to IGNOU Login to Get Every Update